18 September 1997 Execution of queue-scheduled observations with the Gemini 8-m telescopes
Phil J. Puxley
Author Affiliations +
Abstract
Queue scheduling will be one of the major modes of operation of the Gemini 8 m telescopes in which scientific programs will be carried out on behalf of applicants by Gemini staff. Use of a substantial fraction of the available telescope time in this manner will permit access to the exquisite conditions of image quality and background which the telescopes are designed to exploit as well as matching the demands of individual observations to the current conditions. In a previous presentation (SPIE 2871) the classical scheduling and loading of the queue were described. In this paper we discuss the philosophy and parameters which define its execution. Results from detailed simulations of the queue execution process are presented.
© (1997) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
Phil J. Puxley "Execution of queue-scheduled observations with the Gemini 8-m telescopes", Proc. SPIE 3112, Telescope Control Systems II, (18 September 1997); https://doi.org/10.1117/12.278825
Lens.org Logo
CITATIONS
Cited by 4 scholarly publications.
Advertisement
Advertisement
RIGHTS & PERMISSIONS
Get copyright permission  Get copyright permission on Copyright Marketplace
KEYWORDS
Gemini Observatory

Image quality

Telescopes

Device simulation

Clouds

Monte Carlo methods

Optical instrument design

RELATED CONTENT

Gemini queue planning
Proceedings of SPIE (July 12 2008)
Significant issues for field instrumentation systems
Proceedings of SPIE (June 13 1995)
LSST operation simulator implementation
Proceedings of SPIE (June 30 2006)

Back to Top